    MS Project fails to update date fields.

    This is with an existing projects with there are no fixed dates.

    I've noticed this in 2 circumstances:
    First when entering %cent complete. This does not change any dates.
    Second when changing the date of a task that was due prior to "now" but which is being rescheduled for a few days from "now". Again in some unknown circumstances, Project does not reschedule dependent future tasks.
    We've checked dependencies and there are no other fixed dates.

    Has anyone seen these problems and does anyone know of a solution.

  2. #2
    Join Date
    Aug 2006
    Posts
    578

    Lightbulb

    Hi areddy,

    I am not familiar with MS Project, so I doubt I'll be much help.

    -- Are all your service packs and Hotfixes up-to-date for it?
    -- MS seems to offer a good deal of Support ---> Tasks are not scheduled as expected in Microsoft Project


    Hopefully, someone more familiar with this will chime in.

    Best Luck
    PP

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •